🚀 ELN 2.0 CBNC Site Timeline

📅 Latest Update: January 30, 2026
Training and capacity building completed | Lab environment configured | ELN system deployed | 5 SOPs completed

🎯 CBNC IT Progress Summary (Week of Jan 30, 2026)

Category Status Key Achievements
Training & Capacity Building ✅ Completed • Two-week training for In Vivo and Cancer Pharm teams
• Online communication group established
• Continuous documentation updates
Lab Environment Configuration ✅ Completed • Demo presentation completed
• BarTender label printing system integrated
• Caliper, Balance, RFID reader connected
ELN System Configuration ✅ Completed • NC user/group entry and permissions assigned
• ELN-NC hierarchy established
• Single Sign-On (SSO) configured
SOP Standardization ✅ Completed • 5 SOP documents completed:
  - ELN User Manual
  - User Account Management
  - System Configuration Management
  - Data Backup and Recovery
  - Change Control
• Pending activation in Veeva system
Printing Deployment ✅ Completed • Office printer connected and installed
• ELN label printer configured
System Validation 🔄 In Progress • IQ completed
• OQ/PQ validations in progress
• DocuSign process for validation documents

📋 Next Week's Work Plan

📊 Updated Implementation Timeline - Onsite Activities

Completed
In Progress
Planned
Training
Validation
Workstream Dec '25 Jan '26 (Week 1) Jan '26 (Week 2) Jan '26 (Week 3) Jan '26 (Week 4) Feb '26
IT Preparation
VPN • HW
Network Ready
AWS Server Deployment
Jan 6 Deploy
Server Config
Onsite Training
In Vivo • CP Training
Jan 27-31
CP Training
Lab Environment Setup
Device Integration
Animal Facility
Final Config
ELN System Config
SSO Setup
User/Group Entry
Hierarchy Done
SOP Documentation
Draft
5 SOPs Completed
Veeva Activation
Printing System
Office + Label Printer
System Validation (IQ/OQ/PQ)
IQ Done
OQ Testing
PQ Testing
Sign-off
Hardware Procurement
Requisition
Jan 14 Delivery
Installation
Equipment ID
Go-Live Preparation
Readiness Check
Go-Live

🎬 Onsite Team Activities (Jan 14-31, 2026)

Date Range Team Members Key Activities Status
Jan 14-17 Ryan, Saihui, Manny Initial setup, hardware installation, network verification ✅ Completed
Jan 20-24 Ryan, Saihui, Manny In Vivo & Cancer Pharm training (2 weeks), Lab device integration ✅ Completed
Jan 27-31 Ryan, Saihui, Manny Continued training, ELN configuration, SOP finalization 🔄 In Progress
Feb 3-7 TBD Additional CP training, video recording, animal facility config ⏳ Planned

✅ Key Milestones Achieved

🔜 Upcoming Critical Path Items

🚨 Risk & Mitigation

Risk Impact Mitigation Status
Validation delays (OQ/PQ) High Prioritize validation activities; DocuSign ready for rapid sign-off Monitoring
Equipment ID assignment backlog Medium Dedicated resource assigned for week of Feb 3 Planned
Veeva SOP activation delays Medium SOPs ready; coordination with Veeva admin team initiated In Progress
Training coverage gaps Low Video tutorials planned; online support group active Mitigated

Document Version: 2026.1.30 | Next Update: 2026.2.6 | Contact: IT Implementation Team